La Pata Avenue / Del Rio FAQs
What work is currently proposed?
The County has retained consultants to prepare final design plans and construction
documents for the project. The documents will include preparation of final construction
level plans, construction specifications and detailed construction cost estimate.
Preparation of these documents will enable the county to be prepared, when funding
is available, to go out to formal bid and construction of the project. The County
is concurrently proceeding with completing the Federal environmental documentation
that would enable receipt of any federal funding should it become available. The
current efforts are expected to be completed by the end of 2012.
What was the environmental process?
The initial step began in November 2009 with the release of the Notice of Preparation
for the Environmental Impact Report. A public scoping meeting was conducted on December
2, 2009 in San Clemente to provide project information and garner input from interested
parties. A public meeting on the Draft Environmental Impact Report was conducted
November 18th, 2010 in San Clemente to provide interested parties an opportunity
to review and provide comments on the project documents. Public outreach efforts
included numerous community meetings throughout the process. Outreach efforts also
included mailing project information to residents/businesses within a quarter mile
of the project and to key stakeholders/and interested parties. The County's project
Web site was launched and city Web sites included project information for residents.
Press releases were issued to regional and local media. Based on input from the
public meetings the project was refined in the Final Environmental Impact Report
(Final EIR) to address comments received during the Draft Environmental Impact Report
phase.
The Draft Environmental Impact Report was released for a 45 day public review period
on November 3, 2010. The document was available until December 17, 2010. A public
meeting regarding the Draft Environmental Impact Report was held on November 18,
2010.
After the public review period, responses to comments were prepared and the final
environmental document submitted to the County for certification. The County Planning
Commission held a public meeting on the Final EIR April 27, 2011. The Orange County
Board of Supervisors held a public meeting on May 24, 2011 and after receiving public
testimony approved the preferred project alignment and certified the environmental
document.
Where can I review a copy of the Environmental Impact Report?
The Environmental Impact Report can be reviewed under the environmental section
of this web site.
What will the La Pata Gap Closure involve?
"gap" between the two roadway segments and provide an essential link in the local
roadway network. The existing three-lane, 1.8-mile segment of La Pata south of Ortega
Highway will include two additional lanes for a total of five lanes, including a
climbing lane for vehicles bound for the landfill site. From the end of the existing
portion of La Pata south to Calle Saluda, a distance of about two miles, La Pata
and Camino Del Rio will be a new four lane facility.. The La Pata Avenue project
is designed to significantly ease local traffic congestion while minimizing environmental
impacts on the area's high quality of life. The project also provides an alternative
emergency access route for adjacent residential areas..

Why is this project important?
The project is needed to eliminate an existing gap in the County arterial highway
system and establish a connection between Ortega Highway to the north and Avenida
Vista Hermosa and Avenida Pico to the south. These improvements complete the circulation
plans included in both the Talega and Forster Ranch Specific Plans. The project
will also provide direct local connections between the communities of San Clemente,
San Juan Capistrano, Rancho Mission Viejo, Mission Viejo and Ladera along with Los
Flores Ranch. These communities will be able to avoid the congested I-5 freeway
and enjoy improved access to local amenities including schools, shopping, parks
and other recreational facilities. In addition, the completion of the project will
improve mobility for these communities especially in time of local health and safety
emergencies or need for evacuation.
Specific transportation issues that exist within this area of Southern Orange County
include:
- Lack of north-south connectivity of the arterial roadway system
- No arterial highways connecting the County and the City of San Juan Capistrano to
the City of San Clemente (limiting motorists to the I-5 Freeway and Pacific Coast
Highway to travel to or from the city)
- Existing and projected increased congestion on the I-5
- Currently, there is no parallel north-south route to the I-5, in case of emergencies
- Limited transit service
Can you give me a description of the La Pata Gap Closure project?
The
project will provide additional mobility options between San Clemente and the communities
to the west including San Juan Capistrano, Rancho Mission Viejo, Ladera Ranch, Los
Flores and Rancho Santa Margarita.
The La Pata Avenue Gap Closure's northern point starts just 900 feet south of Ortega
Highway at its intersection with Antonio Parkway and La Pata Avenue (a current project
will provide improvements from the Ortega/La Pata intersection to 900 feet south
of the intersection). From this point, La Pata Avenue continues south as an existing
three lane paved roadway through unincorporated territory, just east of the City
of San Juan Capistrano. Two new lanes will be added to this section of roadway,
for a total of five lanes. This roughly 1.8-mile existing section of La Pata Avenue
ends at the County's Prima Deshecha Landfill site. From that point, a new four-lane
La Pata Avenue would extend south just east of the existing Southern California
Edison and San Diego Gas and Electric power-line corridor.
The project remains east of the power-line facilities as it enters San Clemente's
northern City limits. As the project nears the Talega residential development, the
roadway curves west away from the Talega development as it crosses the power-line
corridor. Shortly after it crosses the power-line corridor, it turns south to connect
with existing La Pata Avenue at Calle Saluda in San Clemente. A new meandering eight
foot wide multi-purpose trail is planned for the eastern side of La Pata between
Calle Saluda and Vista Montana. Existing trail connections will be maintained.

Can you give me a description of the Camino Del Rio Extension?
The Camino Del Rio extension is a project planned by the City of San Clemente.
What are the next steps and timelines?
The current schedule is as follows:
- The current project design efforts are expected to be completed by the end of 2012.
The County is concurrently proceeding with completing the Federal environmental
documentation that would enable receipt of any federal funding should it become
available.
- Construction is anticipated to begin Spring/Summer 2013, dependent upon funding
availability.
- Construction is anticipated to be complete in early 2015

What is the relationship with the La Pata Gap Closure and the Foothill Transportation
Corridor-South (FTC-South)?
There is no direct relationship between the FTC-South and La Pata Gap Closure. These
facilities serve different travel needs. The FTC south primarily serves regional
traffic while the La Pata Avenue project will primarily serve traffic between the
local communities.
How would construction be funded?
The project construction costs are estimated at roughly $70 million. Construction
of the project is dependent on the availability of funds. The proposed funding is
anticipated to come from a variety of sources including local, regional and developer
funding. As part of Rancho Mission Viejo's development and the Talega development
plans, some developer funding is obligated to the project. The current funding plan
is;
City/Developer Fees……………………….$10 million
County /Developer Fees…………………...$25 million
State (CMIA) funds……………………….$15 million
Orange County Renewed Measure M……..$10 million*
Shortfall…………………………………….$9 million
*The County has secured $10 million from Measure M and is seeking an additional
$10 million allocation during the next call for project scheduled for the later
part of 2012.
How can I stay informed??
As design efforts proceed we will continue to:
- Issue press releases at critical phases
- Provide updates to surrounding cities
- Stay informed through the County Web site
- Obtain information from your city's Web site.
- Sending us your
questions or comments (see below)
How can I receive information about the project?
There are a number of ways you can receive information on the project. You can contact
the County Project Manager, Mr. Harry Persaud via e-mail, regular mail or by phone
through the information provided below. Information is also available on the following
web sites, which are periodically updated with important information.
Project Manager: Harry Persaud
County of Orange
300 North Flower, 5th Flr Santa Ana, CA. 92703-5000
Tel:
714.667.9655
Email:
Harry Persaud
Planned Communities Home Page
www.san-clemente.org
www.sanjuancapistrano.org
If you have not attended a meeting lately, contact the following to be added to
our mailing list:
LaPataProject
Sending us your questions or comments
|